Project Details
-
Nationwide program
-
Building Size: 700k – 1.3 million square feet
-
Baseline Annual Utility Spend: $0.5 – $4.0 million
Overlay Services
-
Retro-Commissioning Services
-
Investigation, functional testing, and analysis of energy consuming building systems
-
Generation of comprehensive study of Energy Cost Reduction Measures (ECRMs)
-
Implementation of ECRMs selected by client
-
Overview:
-
Overlay Consulting provides comprehensive energy efficiency Retro-Commissioning studies for numerous Amazon Fulfillment Centers throughout the U.S.
-
The team targets projects that result in less than a three-year payback.
-
Energy savings projects are selected by Amazon based on feasibility and financial requirements
-
Overlay Consulting works with local vendors to implement selected projects
Results:
-
Overlay Consulting provides Amazon with Retro-Commissioning Studies at numerous sites identifying energy savings projects ready for rapid implementation that could be completed prior to peak operating season